Project Challenges
Interaction with Mine operations. Mitigation of effects from extreme weather events during construction of works.
Project Approach & Objectives
Locate suitable embankment fill material for placement within levee construction. Implement an accelerated program to
deliver project before wet season. Complete project within time and quality constraints with no environmental or safety
incidents (zero LTIs).
- Supply of all project planning documentation
- Management of all Site Inductions
- Management of vehicle and equipment pass outs
- Remote site establishment
- Survey set-out and control
- Erosion and Sediment control.
- Levee construction in accordance with contract documents, design drawings and construction specifications
- Borrow and blend material to conform to project specification
- Testing in accordance with RPEQ specification
- Provision of QA/QC documentation, daily construction reports, as-constructed surveys and drawings
- Site clean-up and demobilization