Project Elements include:
- Stabilise upstream embankment with 30m wide weighting berm downstream and associated drainage;
- Excavate the spillway channel to improve discharge to Burnett Creek and generate suitable material for weighting berm;
- Assist in the co-ordination of dam instrumentation relocation and existing services.
- 32,826 m2 Clearing and Grubbing
- 71,543 m2 Topsoil stripping and replacement
- 195,000 m3 Excavation for Spillway
- 158,000 m3 Berm Embankment
Construction Fleet consists of:
- D9T Dozer
- PC850 Excavator
- 3 x HD465 50T Rear Dumps
- CAT 16H Grader
- CAT 825H Compactor
- Watercart (16kl)
- Service Vehicle