Project Challenges
Despite the early onset of the wet season and the COVID lock down, the project was completed within an accelerated
program.
Construction of access road for bulk excavation and removal of the existing water structures and materials for future site
use. Locally sourced and conditioned materials enabled effective placement and compaction for sediment dam’s
constraints. A shorter program made coordination with supplier’s paramount to timely completion.
Key Results
- 37ML & 67ML Sediment Dam construction
- Installation pumping systems and associated PE piping, HDPE release structures including concrete encasement, aprons, headwalls required for water transfer
- Landscaping, topsoil and Hydro mulching of all project working areas
- Supply and installation of rock protection
- Construction of approximately 3.2km of LV access track to remove the LV/HV interactions
- Culverts, Concrete cut-off walls, causeway and road pavements
- Installation of fuel pod, MCC Unit and associated PE piping for water transfer
- Sourcing of zoned embankment fill through test pitting
- Erosion and sediment control infrastructures
- All general land rehabilitation
- Cut to spoil with topsoil management and stockpiling