The project scope consisted of the removal of 7 Million cubic metres of material to tight time constraints. Plant utilised were PC 1100 Komatsu excavators with a fleet of 50T Rear Dump Trucks. Final trim batter work was undertaken with several PC 300-8 excavators (with GPS) providing fast efficient and pegless operations. AE graders were utilised in the bulk earthworks crews for haul road maintenance and management of fills and was accomplished by our skilled final trim operators with GPS capability.
The large volumes of material hauled through the project required our fleet to interact with other construction traffic extensively and was achieved without incident and to the satisfaction of our client.