The Wash Bay will support the ongoing maintenance of heavy plant and equipment required to operate the mine.
The client is extremely happy with our consistency in delivering projects that are completed under budget and delivered on-time.
Adding to our pursuit in continued Environmental Management, we relocated local frogs that would gather in the wash pad sump pit in the inclement rains.
- Total Wash Bay Area – 514.3m2
- Reinforced concrete footings, concrete walls, floor and footpaths.
- Concrete Formed Sump Pit
- Concrete Formed Baffle Water Separation Walls
- Pump House Construction
- Gantry Crane Slab Construction
- Wash Bay Gantry Installation